- Construction Time
- Construction Site
Shangrao, Jiangxi
- Project Type
Underground mine
- Equipment Type
Anchor car
Project Introduction: Applied in Ciwu Mining in Shangrao, with ore hardness of F9-F11 and developed joints in some areas.
Construction Efficiency: Single-hole drilling depth of 20-30m, average pure drilling speed of 1.8m/min per hole, average rod changing time of 10-20s per rod.